Ordinary Meeting

 

 

Meeting Date:     Tuesday, 22 May, 2018

Location:            Council Chambers, City Administrative Building, Bridge Road, Nowra

Time:                   5.00pm

 

Membership (Quorum - 7)

All Councillors

 

 

 

 

Addendum Agenda

 

Reports

CL18.124..... Shoalhaven River Pontoons........................................................................... 1

CL18.125..... Berry Broughton Vale RFS Station Site Works.............................................. 4

CL18.126..... Tenders - Kioloa Rural Fire Station Extension............................................. 12 

Confidential Reports        

CCL18.12.... Tenders – Kioloa Rural Fire Station Extension

Local Government Act - Section 10A(2)(d)(i) - Commercial information of a confidential nature that would, if disclosed prejudice the commercial position of the person who supplied it.

There is a public interest consideration against disclosure of information as disclosure of the information could reasonably be expected to reveal commercial-in-confidence provisions of a contract, diminish the competitive commercial value of any information to any person and/or prejudice any person’s legitimate business, commercial, professional or financial interests.

                

 

 


 

Addendum Agenda - Ordinary Meeting – Tuesday 22 May 2018

Page 0

 

 

CL18.124   Shoalhaven River Pontoons

 

HPERM Ref:       D18/166397

 

Group:                Assets & Works Group 

Section:              Asset Management  

Purpose / Summary

A Councillor Briefing was undertaken to discuss this project on Wednesday 17 May 2018.  This report provides an updated budget and allows Council to reconsider the project based on this information. It is recommended this report and recommendation be considered in conjunction with and replace Item SA18.107 on the business paper.

Recommendation

That Council:

1.    Proceed to tender for the additional pontoon project at Greys Beach North Nowra. This will require an additional budget of approximately $4,400 (exc GST) funded from savings in the Local Road Repair Program Callala Beach Road Stage 1 (Job No. 85877).

2.    Proceed with the Shoalhaven River Special Event Pontoon Project minimising costs by using flexible anchorage. This will require an additional budget of approximately $63,000 (exc GST) funded from savings in the Local Road Repair Program Callala Beach Road Stage 1 (Job No. 85877).

 

 

Options

 

Options

1.   As recommended

Implications:

a) Whilst a flexible anchoring system will be designed and certified by a qualified maritime engineer, the risk remains that the anchoring system will not be as robust as a rigid piled anchoring system. The risk of failure is elevated during flood events.

b) The asset life of a flexible anchoring system is expected to be approximately 20 years, which is less than a rigid piled system (40 years); however, piles could be retrospectively fitted if funding was available.

 

2.   Proceed with the current designed higher cost engineered rigid pile system.

Implications: Not affordable within current budget and Council would need to identify an additional funding source.

 

3.   The Greys Beach project will still require rigid piles because of its intended use by commercial vessels however smaller piles with a breakaway system to restrain the pontoons during flood will be allowed as part of the design and construct process.

 

Background

This report relates to two separately funded projects. These are:

1.   Greys Beach Boating Upgrade/Pontoon – part funded from the NSW Boating Now Program.

Stage One of the project has been completed that incorporated design works for the foreshore/carpark (construction not funded) and upgrading of the boat ramp manoeuvring area.

Stage Two relates to provision of a pontoon system on the upstream side of the existing Greys Beach ramp that will be suitable for use by both recreational and larger commercial boats such as the Shoalhaven River ferry.  Provision of an upgraded heavy-duty pontoon at Greys Beach was identified by Council in 2012 (MIN12.1058). An upgraded pontoon will allow the Shoalhaven River ferry (and other commercial users) to use this facility instead of Nowra Wharf which is more restrictive in terms of parking and pedestrian accessibility. This project has strong support from aged and disability groups.

2.   Shoalhaven River Special Event Pontoons to support the Shoalhaven River Festival and other special events.

Second hand pontoons were purchased in 2016 and were used for the river festival in 2016 and 2017 using temporary anchorage.

Detailed design and environmental approval have been completed for both projects.

Council sought targeted quotations in 2017 for installation of rigid piles to support both projects. Only one response was received that significantly exceeded budget. To minimise project costs, Council staff have since been exploring alternative low-cost design solutions for both projects including:

·    Lower cost/higher risk pontoon anchoring systems.

·    Incorporation of the special event pontoons into the Greys Beach project to minimise both pontoon and mooring requirements.

 

Community Engagement

The projects were advertised in 2017 and no negative comments were received, both projects have relevant environmental approvals in place and are ready for construction.

 

Financial Implications

$219,000 balance is remaining in the Greys Beach Project (Job 82700) from a budget of $400,000 that has been part funded with a $295,000 grant from the NSW Boating Now Program, and a Council contribution of $105,000.

There is no funding remaining in the Shoalhaven River Special Event Pontoons Project.

Budget required to complete both project (using flexible anchoring) is estimated as follows:

 

Item

Greys Beach Pontoon

Special Events Pontoons

Lower cost flexible anchor design and certification

$5,000

$5,000

Pontoon

$80,000

existing

Piles (including mobilisation)

$70,000

Not used (Note B)

Walkway/gangplank

$68,400

$18,000 (Note A)

Flexible anchoring

 

$40,000

Total

$223,400

$63,000

Budget available

$219,000

$Nil

Estimated Budget Shortfall

$4,400

$63,000

 

Note:

a)   Nowra Sailing Club was successful in obtaining a grant of $17,760 for the NSW Sports grants for provision of one walkway at Nowra Wharf. Installation of an additional walkway (already purchased) needs to be funded at the second pontoon location adjacent Nowra Rowing Club ($18,000 allowed).

b)   Rigid piling (if utilised) would incur an additional cost of $50,000, plus mobilisation / demobilisation which can be variable upon market demands.

 

*****

 

As discussed with the CFO, the remaining funds from the Local Road Repair Program project Callala Beach Road Stage 1 (Job No. 85877) could be redirected to the wharf project at Greys Beach. A rehabilitation project was completed on Callala Beach Road this year, but rehabilitation was combined with grant funded upgrades to the intersection with Forest Road, providing savings. A second stage of works on Callala Beach Road are planned for the balance as per the Local Road Repair Program if funds were not required to balance overspends.

 

Risk Implications

1.   Minimising damage to pontoons and preventing the assets from floating downstream during major flood events is the largest risk. To mitigate the risk, it is proposed that safety lines be provided similar to what is provided on the current light duty floating pontoon facility located on the downstream side of the existing Greys Beach boat ramp.

2.   There remains a risk that tenders may exceed budget for the Greys Beach project.

 

 


 

Addendum Agenda - Ordinary Meeting – Tuesday 22 May 2018

Page 0

 

 

CL18.125   Berry Broughton Vale RFS Station Site Works

 

HPERM Ref:       D18/167401

 

Group:                Assets & Works Group   

Attachments:     1.  Request for Funding Support - Broughton Vale / Berry Rural Fire Station - Site Works   

Purpose / Summary

The Purpose of this report is to allow Council to consider funding options for the proposed Berry Broughton Vale RFS Station. This report is only necessary and to be considered in conjunction with Item CL18.108, if the rescission motion (Item CL18.107 on the business paper) is CARRIED.

Recommendation

 

That with respect to the proposal to construct a new Berry & Broughton Vale Rural Fire Services Station Council:

1.    Bring forward the replacement of the effected water mains that run through the site (given that the development that impacts on the mains is for the provision of emergency services facilities) at an estimated cost of $160,000 exc GST; and

2.    Fund the water main works from the Water Fund budget, 2018-2019 financial year, [excluding any works that are legitimately funded by the NSW Ambulance project (ie as per their DA Consent 17/1597)];

3.    Complete the site improvement works (estimated cost $410,000) in the 2018-2019 financial year using General Fund loan funds; and

4.    Continue to make representations to the State Government to fund the complete Project costs for this station under the RFS budget process (future years if necessary) so council ultimately only pays it’s 11.7% share.

 

 

Options

Option 1: This is the position adopted by Council at the Ordinary Meeting on the 24 April 2018. If the rescission motion is defeated this will by default be Council’s position.

 

That Council advises the District Manager, Shoalhaven RFS that Council is unable to fund the estimated $400,000 (exc GST) additional cost of the Berry & Broughton Vale Rural Fire Service Station.

Advantages (as outlined on the 24 April 2018)

·    this position is consistent with Council’s current practice with regards to assisting the State Government

·    nil additional cost to Council and council’s share remains at the 11.7% based on the 20-year average cost of RFS services

·   

Disadvantages (as outlined on the 24 April 2018)

·    May lead to a reduced scope of works and project delays

 

Option 2: If the rescission motion is carried a co-funding arrangement could be:

 

That with respect to the proposal to construct a new Berry & Broughton Vale Rural Fire Services Station Council:

1.    Bring forward the replacement of the effected water mains that run through the site (given that the development that impacts on the mains is for the provision of emergency services facilities) at an estimated cost of $160,000 exc GST; and

2.    Fund the water main works from the Water Fund budget, 2018-2019 financial year, [excluding any works that are legitimately funded by the NSW Ambulance project (ie as per their DA Consent 17/1597)];

3.    Complete the site improvement works (estimated cost $410,000) in the 2018-2019 financial year using General Fund loan funds; and

4.    Continue to make representations to the State Government to fund the complete Project costs for this station under the RFS budget process (future years if necessary) so council ultimately only pays it’s 11.7% share.

 

Advantages

·    Seeks to provide a compromise solution so the project can proceed.

·    Clearly outlines Council’s support for the proposal

·    Seeks to have the State Government accept that the total costs of such projects should be recognised within normal RFS budget process rather than expect council ratepayers to pick up additional costs associated with the complexities of this site.

 

Disadvantages

·    May create an expectation that similar support will be provided for future projects.

 

Option 3: If the rescission motion is carried Council determine a different option.

 

Background

At the Ordinary Meeting on the 24 April 2018 Council resolved as follows (Vide minute no MIN18.314)

“That Council advises the District Manager, Shoalhaven RFS that Council is unable to fund the estimated $400,000 (exc GST) additional cost of the Berry & Broughton Vale Rural Fire Service Station.”

This report is provided as Attachment 1 for Councillors convenience.

 

Following this decision, a rescission motion was lodged, and thus this resolution has not been acted upon.

 

The rescission motion was discussed at the Strategy & Assets Meeting on the 15 May 2018 at which the matter was deferred to the Ordinary Meeting on the 22 May 2018

 

At a Councillor briefing held on the 17 May 2018 the following points were made:

 

·    Council’ contributions to RFS recently (ie 11.7% of Rural Fire Fighting Fund minus Volunteer and Statewide Support – VASS contributions) Source: report to Council 19 April 2016.

            Total Council

2014/2015       $922,287

2015/2016       $943,589 approx

2016/2017       $921,258 approx

·    The proposed site (old North Street Road Reserve) is Council owned

·    The land value of the site would be in the vicinity of $500,000.

·    The site requires manoeuvring of RFS vehicles on the adjoining NSW Ambulance site.

·    The NSW Ambulance Site works have progressed with changes to the approved plans (DA17/1597). The changes affect the RFS site (fill quantities and water services works) and at the time of writing this report the entity responsible for approving the changes was unknown.

·    The revised Preliminary Estimate of costs is for the RFS proposal

 

Concept Design (Actual)

$23,858.30

Detailed Design and Approvals

$86,300.00

Site Costs (Note this has increased slightly since the 24 April 2018 report)

$410,000.00

Water Main

$159,280.00

Construction Costs

$912,421.00

Total

$1,591,859.30

 

·    The completed RFS building will become a Council asset (based on the existing State/Local Government arrangements).

·    At this stage the RFS has not committed funding to the construction of the station other that $50,000 to complete concept plans and formal consents.

 

Water Main

 

The RFS site is the old North Street Road Reserve and thus the site contains two Water Mains owned by Council. The water mains are old AC style mains and will need to be reconstructed prior to the site being modified to accommodate the RFS building. These mains run close and parallel to the NSW Ambulance boundary and it was understood (based on the development consent) that the NSW Ambulance works would include reconstruction of the full length of the water mains through the RFS site as part of their works, (which encroached onto the RFS land). Given the site works undertaken to date (ie the construction of a retaining wall along the shared boundary, the approval of which was not clear at the time of writing this report) it is thought that the bulk of this reconstruction will be undertaken by the NSW Ambulance Service.

 

Option WM1: Council not fund the works as the remaining life is more than a few years and thus the cost to reconstruct the water main is not in Council short to medium works programs.

 

Option WM2: Given that the development is impacting on the water main is relating to the provision of emergency services, Council funds the mains reconstruction works that is not legitimately funded by the NSW Ambulance project (ie as per their DA Consent 17/1597). Council bring forward the replacement of the effected water mains that run through the site (estimated cost $160,000 exc GST) and fund the works in the 2018-2019 financial year, excluding any works that are legitimately funded by the NSW Ambulance project (ie as per their DA Consent 17/1597).

 

Detailed Design

 

At this stage the detailed design work has not been undertaken and thus a construction budget with a high degree of certainty is difficult to ascertain. Recent experience with other RFS construction sites is as follows;

 

 

Allocation

Lowest Tender

Contingency

Shortfall

% increase

Kangaroo Valley

$400,000

$582,168

$17,832

$200,000

50%

Kioloa

$370,000

$589,282

$10,718

$230,000

62%

Shoalhaven Heads

$675,000

$975,344

$19,507

$319,851

47%

 

Committing to construction of the station prior to Detailed Design work being completed and estimates (based on local market conditions) could result in a high risk of inadequate funding being allocated.

 

Option DD1: That Council supports the allocation of RFS funds (to which Council contributes approximately 11.7% based on the 20-year average cost of RFS services) for the detailed building design work in 2018-2019 and thus allow an accurate Construction Cost to be determined for allocation by the State Government in future years.

 

Option DD2: That Council leave this matter for the RFS to manage. Construction funding bids may be competitive and funding from the State Government may not be available for construction after 2018-2019.

 

Site Works

 

The RFS site requires 1 to 2 metres of fill across the site and a retaining wall along the northern edge of the building footprint. Ideally these works should be done well in advance of the building construction to minimise the risks and variables in pricing the building work. The RFS has requested that Council fund these works with the view that in providing the land for the site the Council should make land available that is ready for building works to proceed.

 

Option SW1: Given that the development is for the provision of emergency services and Council owns the land on which the development is proceeding that Council fund the site improvement works and that given maturity of the 2018-2019 draft budget process these works be funded from loan funds.

 

Option SW2: That Council advise the RFS (District Manager, Shoalhaven) that Council is unable to fund the estimated $410,000 (exc GST) additional cost of the Berry & Broughton Vale Rural Fire Services Station.

 

Policy Implications

Option two would be a departure from Council’s current practice which is to not assist the State Government with funding for services that it is responsible for.

 

Financial Implications

Option two is unfunded in Council’s long term financial plan, however if the allocation is made during the budget adoption process these implications will be managed at that point.

 

For Councillors information, a commercial loan of $400,000 would attract an accumulative interest bill of approximately $90,000 over ten years. An internal loan from one of council’s  Reserves (assuming funds are available) would attract $0 interest. The CFO will be presenting a report to the same Council meeting outlining the strategy here, if loan funding is required.

 

The NSW Ambulance Station and the Proposed RFS Station have been co-located at Berry to reduce the total site footprint and reduce the area and cost of pavement required to manoeuvre vehicles. Perhaps Council could make a request to the State as follows:

 

That Council write to the State Member Garth Ward MP seeking support for any savings from the construction of the NSW Ambulance Station at Berry being made available to the proposed NSW Rural Fire Service Station given that the Ambulance Station and the proposed RFS Station have been collocated at Berry to reduce the total site footprint and reduce the area and cost of pavement required to manoeuvre vehicles.

 

 


 

Addendum Agenda - Ordinary Meeting – Tuesday 22 May 2018

Page 0

 

PDF Creator


 

PDF Creator


 

PDF Creator

 


 

Addendum Agenda - Ordinary Meeting – Tuesday 22 May 2018

Page 0

 

 

CL18.126   Tenders - Kioloa Rural Fire Station Extension

 

HPERM Ref:       D18/167870

 

Group:                Assets & Works Group 

Section:              Project Delivery & Contract  

Purpose / Summary

To inform Council of the tender process for Kioloa Rural Fire Station Extension.

In accordance with Section 10A(2)(d)(i) of the Local Government Act 1993, some information should remain confidential as it would, if disclosed, prejudice the commercial position of the person who supplied it. It is not in the public interest to disclose this information as it may reveal commercial-in-confidence provisions of a contract, diminish the competitive commercial value of any information to any person and/or prejudice any person’s legitimate business, commercial, professional or financial interests. This information will be considered under a separate confidential report.

This report is submitted directly to the Ordinary Council Meeting pursuant to Clause 3 of Council’s “Acceptance of Tenders – Reports to Council” Policy.

 

Recommendation

That Council consider a separate confidential report in accordance with Section 10A(2)(d)(i) of the Local Government Act 1993.

 

 

Options

1.    Consider the separate confidential report.

2.    Council could propose an alternative.

 

Details

Council called Tenders for the Kioloa Rural Fire Station on 13 February 2018 which closed at 10:00am on Tuesday 6 March 2018.  One (1) tender was received at the time of closing and is shown in the table below:

 

Tenders Received

Tenders were received from the following:

Tenderer

Location

Edwards Constructions (NSW) Pty Ltd

Nowra 2541

 

Details relating to the evaluation of the tenders are contained in the confidential report.

 

Financial Implications:

Funding is sourced from Rural Fire Service budget for 2017/2018.